MVP roadmap Gantt chart template

A 12-week MVP roadmap covering problem validation, scope cut, design, build, beta and launch, for founders shipping the first version of a software product.

Duration
12 weeks
Phases
6
Tasks
27
Format
.gantt
MVP Roadmap27 tasks · 6 phases · 12 weeks
MVP Roadmap Gantt chart: 27 tasks across 6 phases over 12 weeks
The template as it opens in the app. Its example dates start on 1 June 2026. Change them to fit your project.

About this template

Most MVPs ship 3–6 months late because the initial scope was too ambitious. The fix is not better project management. It is brutal scope cutting up front. This 12-week template assumes the problem is already validated with 5–10 potential customers and the team is genuinely ready to build. If the problem is not validated yet, do not skip phase 1: that is the phase that prevents the wrong MVP.

How a 12-week MVP roadmap breaks down

01

Problem validation

Weeks 1–2

Interview 10–20 people in your target ICP. Find the 3–5 strongest pain points. The strongest signal is people offering to pay before the product exists. Document the problem space in one page. If interviews do not produce a clear single pain point, do not start building. Keep talking to people.

Steps in this phase
  • Identify 20–30 interview targets
  • Conduct 10–20 interviews
  • Synthesize top pain points
  • Single-page problem statement
  • Validate by pre-selling if possible
02

Scope cut

Week 3

List every feature anyone has ever suggested. Cut to 5–8. Cut again to 3–5. The MVP is what solves the core pain point and nothing else. Anything labeled "would be nice" is a future feature, not an MVP feature.

Steps in this phase
  • Brainstorm full feature list
  • Cut to 5–8 must-haves
  • Cut again to 3–5 core MVP features
  • Define success criteria
  • Identify the one metric that matters
03

Design

Weeks 3–5

Wireframes for every screen in the MVP. High-fidelity designs for primary flows only. Skip the design system if you can: pick a UI library and ship. Get 5 people to click through the prototype. The fast feedback prevents building things nobody wants.

Steps in this phase
  • Wireframes (every screen)
  • High-fidelity for primary flows
  • Pick UI library (skip custom system)
  • Click-through prototype
  • 5-user feedback loop
04

Build

Weeks 4–10

Build the 3–5 features. Hosting, auth, database, basic admin. Resist the urge to add features mid-build: every addition delays launch by 1–2 weeks. Stand-up daily so blockers surface fast. Demo to a friendly user every Friday.

Steps in this phase
  • Hosting and auth setup
  • Database schema
  • Feature 1
  • Feature 2
  • Feature 3
  • Basic admin
  • Friday user demos
05

Beta

Weeks 9–11

Onboard 5–20 beta users from the original interview list. Daily contact. Track what they actually use vs. what they say they want. The gap is your real insight. Fix the top 3 blockers each week. Capture testimonials from anyone who has a "wow" moment.

Steps in this phase
  • Onboard 5–20 beta users
  • Daily check-ins
  • Track actual usage
  • Fix top 3 blockers per week
  • Capture testimonials
06

Launch

Week 12

Public launch: Product Hunt, Hacker News, LinkedIn, customer email. Pricing live. Onboarding tested. Support email monitored. Plan for a week of chaos, because every MVP launch surfaces issues that beta did not.

Steps in this phase
  • Product Hunt launch
  • Hacker News (Show HN)
  • LinkedIn announce
  • Customer email
  • Pricing live
  • Support monitoring

Tips from MVPs that shipped on time

  1. 01

    Cut scope twice. The first cut is too generous; the second one is closer to honest.

  2. 02

    Pre-sell before building if you can. The strongest validation signal is money.

  3. 03

    Demo to a real user every Friday. The fast feedback prevents building things nobody wants.

  4. 04

    Resist mid-build feature additions. Every "small" feature delays launch by 1–2 weeks.

  5. 05

    Plan for chaos in the launch week. Every MVP surfaces issues that beta did not.

Questions

How long should an MVP take?

8–16 weeks. Anything longer than 4 months is rarely an MVP. It is a full product disguised as one.

How do I know the problem is validated?

When 10+ people in your ICP describe the same pain in their own words AND a meaningful fraction offer to pay before the product exists.

Should I bring on a co-founder before MVP?

Most successful founders say yes: solo MVPs that succeed are rare. But the co-founder fit matters more than the timeline.

Start with this template

Open the MVP roadmap template, fit it to your timeline, and you have a working 12-week plan from validation to launch.