Restaurant opening Gantt chart template

A 6-month restaurant opening plan covering concept, location, permits, build-out, equipment, menu, hiring, marketing and soft launch, for first-time and second-time restaurateurs.

Duration
6 months
Phases
6
Tasks
31
Format
.gantt
Restaurant Opening31 tasks · 6 phases · 6 months
Restaurant Opening Gantt chart: 31 tasks across 6 phases over 6 months
The template as it opens in the app. Its example dates start on 1 June 2026. Change them to fit your project.

About this template

Restaurants open late more often than on time. The single biggest cause is permitting: health, fire, building and alcohol permits all run in parallel, and any one of them can block the opening. This 6-month template assumes the lease is being negotiated when month 1 starts. Add 2 months to the front if location is not yet identified. Most experienced restaurateurs plan 9–12 months from lease signing.

How a 6-month restaurant opening breaks down

01

Concept and lease

Month 1

Refine the concept: cuisine, service style, price point, target customer. Identify and negotiate the lease. Engage attorney for lease review. Engage architect or designer. Submit business license and EIN paperwork. Open business bank account.

Steps in this phase
  • Refine concept
  • Negotiate lease
  • Attorney review
  • Engage architect/designer
  • Business license
  • EIN and bank account
02

Design and permits

Months 2–3

Architectural drawings. Submit for building permit, health department review, fire marshal review, and (if applicable) alcohol license. Each takes 4–12 weeks and runs in parallel. Order long-lead equipment: major kitchen equipment can be 8–14 weeks.

Steps in this phase
  • Architectural drawings
  • Submit building permit
  • Health department review
  • Fire marshal review
  • Alcohol license application
  • Order long-lead equipment
  • Smallwares list
03

Build-out

Months 3–5

Demolition (if needed). MEP rough-in (mechanical, electrical, plumbing). Hood and gas line install: restaurant-specific. Drywall, paint, floor. Front-of-house furniture and design. Kitchen equipment delivery and install. Final inspection.

Steps in this phase
  • Demolition
  • MEP rough-in
  • Hood and gas line
  • Drywall, paint, floor
  • FOH furniture
  • Kitchen equipment install
  • Final inspection
04

Menu and recipes

Months 3–5

Develop the menu in parallel with build-out. Source ingredients and confirm distributors. Cost every dish: aim for 28–32% food cost. Standardize recipes. Train head chef and sous chef on the full menu. Conduct tasting with key stakeholders.

Steps in this phase
  • Develop menu
  • Source ingredients and distributors
  • Cost every dish (28–32%)
  • Standardize recipes
  • Stakeholder tasting
  • Print menus
05

Hire and train

Months 4–6

Hire FOH manager, head chef (already in concept), sous chef, line cooks, servers, bartenders, bussers. Onboard in 2 waves: kitchen staff 4 weeks before opening, FOH 2–3 weeks before. Training: menu, service standards, POS, opening and closing checklists. Do staff meals to practice menu execution.

Steps in this phase
  • Hire FOH manager
  • Hire kitchen staff
  • Hire FOH staff
  • POS setup and training
  • Service training
  • Menu training (kitchen)
  • Staff meals (practice)
06

Marketing and soft launch

Month 6

Website, Google Business Profile, Instagram. Local PR pitches. Friends-and-family soft launch: 2–4 nights to stress test before the public opens. Adjust based on what broke during soft launch. Grand opening.

Steps in this phase
  • Website live
  • Google Business Profile
  • Instagram and social
  • Local press outreach
  • Soft launch (friends and family)
  • Adjust based on soft launch
  • Grand opening

Tips from restaurants that opened on schedule

  1. 01

    Submit all permits in parallel in month 2. Sequential permits double the timeline.

  2. 02

    Order long-lead kitchen equipment in month 2. Hood, walk-in cooler, and large pieces can be 8–14 weeks.

  3. 03

    Cost every dish before opening. Restaurants without food cost discipline lose money invisibly.

  4. 04

    Run a friends-and-family soft launch. 2–4 dinners catch every operational issue before the public sees them.

  5. 05

    Build a 20% contingency into the budget. Restaurants almost always cost more than projected.

Questions

How long does it take to open a restaurant?

6–12 months from lease signing for most concepts. Fast casual: 4–8 months. Full-service: 8–12 months. Bar-driven concepts often longer due to alcohol licensing.

What is the most common reason restaurants open late?

Permits. Health, fire, building, and alcohol all have to align. Submit all four in month 2.

How much money do I need?

Highly concept and location dependent: $200K for a small fast-casual, $1M+ for a full-service in a major city. Plan for 6 months of operating capital after opening.

Start with this template

Open the restaurant template, fit it to your lease and opening date, and you have a working 6-month plan with the permits, build-out, and soft launch plotted.