Design and permits
Weeks 1–4Nothing on site happens until drawings are stamped and the permit is in hand. Architects and designers need 2–3 weeks to produce permit-ready drawings; the local building department needs another 1–4 weeks to review, depending on jurisdiction. Order long-lead items (cabinets, custom windows, special-order tile) at the end of this phase so they arrive in time for installation.
- Lock in scope and finish-level decisions
- Finalize architectural drawings
- Submit for permit
- Order long-lead materials (cabinets, windows, tile)