Design lock and ordering
Weeks 1–2Confirm the layout, finish selections, and appliance package. Order cabinets immediately. The rest of the schedule depends on when they show up. Order tile, flooring, lighting, and the appliances within the same week so deliveries land before you need them, not after.
- Finalize layout
- Order cabinets (4–8 week lead time)
- Select and order tile, flooring, lighting
- Order appliances