Design, order, demo
Week 1Order the vanity, tile, fixtures, and glass door (custom glass has a 3-week lead time). Demo the existing bathroom (fixtures, tile, drywall) down to the studs. A typical bathroom demo is one to two days for two people. Strip the floor down to the subfloor.
- Finalize tile, vanity, fixtures, glass door selections
- Order materials (especially glass door, 3-week lead)
- Demo to studs and subfloor
- Haul debris