What is a Gantt chart?

A Gantt chart shows every task of a project as a bar on a calendar. You see at once what overlaps and what must wait.

A Gantt chart is a horizontal bar chart that maps the tasks of a project against a calendar. Each task is a bar. The position of the bar shows when the task starts and ends. The length of the bar shows how long the task takes. Put all the bars on one timeline and you see the whole project at once. You see what overlaps and what must wait for another task to finish.

A Gantt chart is a picture of a plan over time. The idea is more than a century old. People still use it for plans as small as a wedding checklist and as large as a satellite launch.

Gantt chart of a website redesign with a task list on the left. Bars show Research, Design, Build and Review, and a diamond shows the Launch milestone. Arrows link each task to the next. A darker part of a bar shows progress. A dashed line marks today. Gantt chart of a website redesign with a task list on the left. Bars show Research, Design, Build and Review, and a diamond shows the Launch milestone. Arrows link each task to the next. A darker part of a bar shows progress. A dashed line marks today.
A Gantt chart has a task list on the left and a timeline along the bottom. Each task is a bar. An arrow shows a dependency and a diamond shows a milestone. A darker part of a bar shows progress. The dashed line marks today.

The parts of a Gantt chart

Almost every Gantt chart has the same seven parts. When you know their names, you can read any chart.

  • The task list runs down the left side. It has one row per piece of work, often grouped into phases.
  • The timeline axis runs across the top or the bottom of the chart. Its marks are days, weeks or months. A longer project needs larger units.
  • The bars are the main part. A bar starts on the start date and ends on the finish date. Its width is the duration.
  • Milestones are events with no length, such as a launch or a deadline. A diamond usually marks a milestone.
  • Dependencies are arrows from one bar to another. They show that the second task cannot start until the first task reaches a set point.
  • Progress shows as a shaded part of a bar. A half-filled bar means the task is about half done.
  • The today line is a vertical marker on the current date. It shows at once if you are ahead or behind.

How to read one

Read a Gantt chart in two directions. Read down the rows to see all the work in the project. Read across one row to see when that task happens. Then make these checks.

  1. Check overlap. Bars that overlap in time happen at the same time. They show where several people are busy at once and where the plan asks too much of them.
  2. Follow the sequence. Arrows show the order of the work and which late task pushes back the tasks after it.
  3. Compare with today. A bar whose shaded part stops before the today line is behind schedule. A milestone to the left of today that is not reached is a missed deadline.

A small worked example

Consider a website redesign. Research of the current site takes 5 days. Design of the new pages takes 1 week. Build takes 2 weeks and review takes 3 days. Launch is a milestone at the end. On the chart, design cannot start until research finishes. Build follows design.

A to-do list shows what to do. A Gantt chart also shows when, and what depends on what. Two facts appear at once that a list hides. The project is about five weeks long. Build is the longest task, so if build runs late, the launch runs late.

What Gantt charts are good at

  • Time and overlap are easy to see. Three bars stacked over March show at once that three tasks happen in March.
  • Dependencies become visible. Arrows show which task must come first, so people can see the order and discuss it.
  • The critical path stands out. It is the chain of tasks that sets the end date. A timeline makes it easy to find.
  • The plan is easy to explain. A stakeholder who does not read project spreadsheets can understand a Gantt chart quickly.

The limits of a Gantt chart

A Gantt chart has limits. People often use one when another tool fits the work better.

  • A Gantt chart assumes that you know the plan. It is weak for research work, where the next step depends on what you learn. A Kanban board suits that flow better.
  • A big chart is hard to use. A chart of 400 tasks is hard to read and harder to keep current. Group tasks into collapsible phases and do not track every small item.
  • A chart goes out of date when nobody updates it. It is only as accurate as its last edit. A plan that nobody revisits is no longer useful.
A short rule

Use a Gantt chart when you know the main tasks and the work has a deadline. It helps most when tasks depend on each other. Use a list or a board when the work is open-ended or the order does not matter.

A short history

The chart takes its name from Henry Gantt, an American engineer. He made it popular in the 1910s to schedule factory and shipyard work. He was not the first. The Polish economist Karol Adamiecki made a near-identical chart, a "harmonogram", around 1896. He published it in Polish and Russian, so people who read English learned the method from Gantt. For decades, people drew these charts by hand on paper. For most of the twentieth century, only large projects were worth that effort. Software changed this. Today you can build a chart in a browser in a minute, so everyday plans can use the method too.

When to use a Gantt chart

Use a Gantt chart when at least two of these four statements are true. The project has a deadline. It has more than a few tasks. The tasks depend on each other. Other people need to understand the plan. A weekend move, a product launch, a dissertation and a kitchen remodel all fit. A grocery list does not, because the time and the order of tasks do not matter.

Questions

Is a Gantt chart the same as a project timeline?

They overlap. A timeline usually shows only when things happen. A Gantt chart also shows task durations, dependencies between tasks and progress. A Gantt chart is a kind of timeline, and many timelines are simpler.

Do I need special software to make one?

No. You can sketch a basic Gantt chart on paper or in a spreadsheet. A dedicated tool is faster to draw, drag and keep up to date. You can build one free in the browser at ganttchartmaker.app with no signup.

How much detail does each task need?

Do not make a task shorter than the smallest unit that you track. If you review the plan every week, tasks of less than a day add noise and give no extra control. Group fine detail under collapsible phases instead.

What is the difference between a task and a milestone?

A task has a duration and appears as a bar. A milestone is a marker with no length for an important moment, such as a deadline or a launch. A diamond usually shows a milestone.