A dependency is a rule that says one task cannot proceed until another reaches a set point. "You cannot paint the wall until the plaster is dry" is a dependency. So is "the press release goes out when the product is live". Dependencies turn a flat list of tasks into a schedule. They decide the order, and they decide which delays spread to other tasks.
In a Gantt chart, dependencies are the arrows that join one bar to another. Most people use only one kind of arrow, and that is usually correct. But there are four types. The other three help when a plan does not fit the usual arrow.
The four dependency types
Every dependency links an edge of one task, its start or its finish, to an edge of another. That gives four combinations. A name reads from the edge of the predecessor to the edge of the successor.
| Type | Means | Plain example |
|---|---|---|
| Finish‑to‑Start (FS) | B cannot start until A finishes. | Plaster must dry before you paint. |
| Start‑to‑Start (SS) | B cannot start until A starts. | The review cannot begin before the draft begins. |
| Finish‑to‑Finish (FF) | B cannot finish until A finishes. | Testing cannot finish before development finishes. |
| Start‑to‑Finish (SF) | B cannot finish until A starts. | The old on-call shift ends only when the new one begins. |
Finish-to-Start (FS), the default
Almost everyone means this type by "dependency". The first task must be done before the second can begin. Build the foundation, then frame the house. Get sign-off, then send to print. It is the most common link by far, and when you are unsure, it is usually the right one. If your tool lets you draw a dependency without a choice of type, it almost certainly creates an FS link.
Start-to-Start (SS), work that runs together
Two tasks run in parallel, but one cannot start before the other starts. A classic case is an editor and an author. The editor can start to review chapters when the author starts to write them. Before that, nothing exists to read. SS links model work that overlaps without a claim that the tasks are fully simultaneous. Add a small lag, for example a review that starts three days after the draft starts. Then the link describes a realistic pipeline.
Finish-to-Finish (FF), work that ends together
Two tasks must end together, or one cannot close until the other does. A team cannot declare quality testing complete until the feature that it tests is complete. A team cannot finalise documentation until the thing that it documents is final. The tasks can start at different times and run at different speeds. FF ties their finish dates together.
Start-to-Finish (SF), the rare handoff
This is the odd one out, and the one you use least. Task B cannot finish until task A starts. The textbook example is a shift handover. The old shift can end only after the new shift has begun, so the post is never uncovered. If you want to use SF, check first that you do not mean FS with the tasks swapped. This is the usual confusion.
Lead and lag time
A dependency does not have to mean "immediately after". You can add lag, a delay, or lead, an overlap, to any link.
- Lag is a wait built into the link. "Hang the cabinets two days after the paint is done" is an FS dependency with two days of lag. The paint needs those days to cure. The second task does not start the moment the first one ends. It starts later.
- Lead, sometimes called negative lag, lets the second task start before the first one finishes. "Begin the user guide when development is 80% done" is a lead. It is a deliberate, controlled overlap that saves calendar time.
Lag and lead let a schedule reflect reality and not an idealised assembly line. Use them on purpose, and write down why the lag exists. Then the next person does not "tidy it up" and break the plan.
Mistakes that damage a schedule
- Do not over-link. Not every task that happens after another one depends on it. If two tasks can run in any order, do not chain them. A false dependency makes your plan look more rigid and more fragile than it is.
- Do not use a dependency for a date. "This starts on the 14th because the contractor is free" is a resource constraint, not a dependency. A pinned date where you need a link hides the real reason. It breaks without warning when things move.
- Avoid circular dependencies. If A waits on B and B waits on A, neither can ever start. Good tools refuse to create the loop. If yours does not, look for a task that the tool cannot schedule.
- Do not link to summary rows. A dependency on a whole phase is a mistake when you need one task inside it. The schedule is technically correct and useless in practice.
How to pick the right type
Check these four cases in order. They cover most situations.
- If B needs the output of A before it can begin, use Finish-to-Start.
- If B can run alongside A but only after A is under way, use Start-to-Start, usually with a lag.
- If B can run independently but must close when A closes, use Finish-to-Finish.
- If the link is a continuous-coverage handover, use Start-to-Finish. Otherwise you probably want FS.
Dependencies and the critical path
Dependencies are more than bookkeeping. Chained together, they form paths through your project. The longest path, the one with no slack, is the critical path. It sets your earliest possible finish date. When the dependency types are right, the critical path shows what drives the finish date and what does not. When they are wrong, the schedule shows the wrong place for the real pressure. Typical causes are too many links and a date that people label as a dependency.
Questions
Which dependency type do I use if I am not sure?
Use Finish-to-Start. It is the most common link. It fits most real dependencies, where one task produces something that the next task needs.
What is the difference between lag and a delay?
They are the same idea. Lag is a delay built into a dependency. The successor starts, or finishes, a set time after the link condition is met, instead of immediately.
Can a task have more than one dependency?
Yes, and many do. A task often waits on several predecessors. It can start only when every condition is met. The latest condition controls its start date.
Are dependencies the same as a task order?
Not quite. Order is the sequence in which things happen. A dependency is an enforced rule about that order. You can do tasks in an order with no dependency between them. Dependencies are the orders that are mandatory.