Slack and float explained

Most tasks can slip a little without harm. Float is the amount, and it shows which delays are safe.

In almost any real project schedule, most tasks are not due when their bar says they start. They have spare room to begin late or to run long before anything bad happens. People call that room float, or slack. The two words mean the same thing. "Float" is more common in formal scheduling, and "slack" is more common in everyday use. Float is easy to overlook. When you can read it, a schedule is more than a list of deadlines. It shows which deadlines are real.

Float shows who feels the delay when a task slips. For some tasks, the answer is "nobody, for days". For others, it is "the whole project, immediately". Float separates the two kinds, so you do not treat every task as equally urgent.

Where float comes from

Float comes from the two-pass calculation behind the critical path method. A forward pass through the network gives every task its early start and early finish. These are the soonest dates at which the task can happen. A backward pass gives its late start and late finish. These are the latest dates at which it can happen without a delay to the end date of the project. Float is the gap between them.

Total float = late start − early start = late finish − early finish.

A task can start on day 3 at the earliest and on day 8 at the latest. It has five days of float. The arithmetic is plain. The meaning of the gap is what matters. The task can absorb five days by a late start, a long run or a mix of both. After that, the delay is no longer the problem of this task alone. It affects the project.

Total float versus free float

There are two kinds of float, and a mix-up of the two causes many scheduling surprises. The difference is who pays when you use the spare time.

Total float, slack before the project slips

Total float is how long a task can slip before it delays the finish date of the project. It is the main number, and many tools show it by default. The formula for float gives it. But total float is often shared along a chain of tasks. Suppose three tasks in a row share six days of total float. That is six days for the chain, and not six days each. If the first task uses them, the two tasks after it inherit a smaller, recalculated float. Total float tells you that the chain has room. It does not promise that the room is yours alone.

Free float, slack before the next task slips

Free float is the stricter, more local measure. It is how long a task can slip before it delays its own immediate successor. That is the next task that depends on it. Free float is the early start of that successor minus the early finish of the current task. It is always less than or equal to total float. It is the safer number to act on, because the delay disturbs nobody downstream. A task with three days of free float can slip three days. The next task still starts when it always starts. You can take that delay without a single conversation.

A worked example

Take three tasks, A then B then C, in sequence. Together they must finish by day 12. The forward pass puts A at early start 0 and early finish 2. It puts B at early start 2 and early finish 5. It puts C at early start 5 and early finish 8. So the chain finishes on day 8, four days before its day-12 deadline. The backward pass gives all three tasks the same four days of total float relative to the deadline.

But the free float is different. B cannot slip at all, because any slip moves the earliest start of C. C starts the moment B finishes. So B has zero free float, even though it has four days of total float. The four days belong to C, the last task before the deadline. C can slip the full four days without a delay to anything after it. Total float makes all three tasks look relaxed. Free float shows that only C can move freely. If you slip B because of its total float, you use up the spare time of C by accident.

A short rule

Read total float to judge the project. Act on free float to judge a single task. Before you let one task slip, check its free float. That number shows whether the delay is free.

Zero float means critical

A task with zero total float has no spare room. Its earliest and latest dates are identical, so any slip pushes the finish date of the project. The zero-float tasks, chained together from start to end, are the critical path. Critical means no float, and a task with float is not critical. These are the same fact stated in two ways. The critical-path tasks deserve your scarce attention, and the tasks with much float can wait. The critical path method lays out the whole logic.

Negative float means you are already behind

Float can go below zero, and that is a warning. Negative float appears when an imposed deadline is earlier than the schedule can deliver. Suppose a chain of work needs until day 14, but someone has committed to day 11. The tasks on that chain carry minus three days of float. They need to start three days before they realistically can, which is impossible. Negative float does not mean "tight". It means that the plan as drawn cannot meet the date, today, before anything has slipped. You have three responses. You can compress the work by crashing or fast-tracking the path. You can cut scope. You can move the deadline. If you ignore the negative number, you only delay the problem. With negative float, planning ends and schedule slippage begins.

How to use float

Float is practical. These are its main uses.

  • Set priorities by float. When two tasks compete for the same person on the same day, the task with less float wins. A zero-float task always outranks a task with five days of float. This holds even if the other task feels more urgent or its stakeholder is louder.
  • Level resources and keep the end date fixed. Float is the room that you have to move work around and relieve an over-committed week. You can move a task with float later to remove a bottleneck. While you stay inside its float, the finish date does not change. This is the basis of resource levelling.
  • Know which delays are safe. "The vendor needs two more days" is no problem for a task with a week of free float. It is a crisis for a task with none. Float lets you answer at once. You do not treat every small change as an emergency. You also do not accept every change without a check.
  • Watch for float that gets smaller. It is an early sign of trouble. A task that had eight days of float last week and has two this week is close to critical. Track the trend as well as the snapshot. A drop in float is a warning that arrives before the team misses any date.

A note on independent float

A third, stricter measure exists. It is independent float. It is the slack that a task has if all its predecessors finish as late as possible. It also assumes that its successors must start as early as possible. It is the spare time that is yours, whatever the tasks next to it do. It is always the smallest of the three and is often zero. Many tools do not show it by default. Know that the term exists. For daily work, use total float for the project view and free float for the task view.

Questions

Are slack and float the same thing?

Yes, they are the same. They are interchangeable terms for the spare time that a task has before it delays something. "Float" is the more common word in formal critical path scheduling and in many software tools. "Slack" appears more in everyday and North American use. The meaning is the same.

What is the difference between total float and free float?

Total float is how long a task can slip before it delays the whole project. It is often shared across a chain of tasks. Free float is how long a task can slip before it delays its own immediate successor. It belongs to that one task alone. Free float is always less than or equal to total float, and it is the safer number to act on.

How is float calculated?

Total float is the difference between the late and early dates of a task. Late start minus early start equals late finish minus early finish. Those dates come from the forward and backward passes of the critical path method. Free float is the early start of the next dependent task minus the early finish of the current task.

What does negative float mean and how do I fix it?

Negative float means that an imposed deadline is earlier than the schedule can deliver. The work needs more time than the date allows, before anything has slipped. You can compress the critical path by crashing or fast-tracking it. You can also reduce scope or move the deadline. The number does not improve until one of those changes the plan.